October 5, 2008

Ag Leader update

Thought I would give a little update on my Ag Leader project. It was about 2 months and one week ago that we started pouring the first of three sections on the second floor. About two months ago we started interior framing.

In that time, we have completely framed the interior, done most all the electrical, heating and cooling work, plumbing, and sheetrock. We are almost half painted and have started the flooring. (In case you forgot or didn't know, there is almost 2 acres of finished area in this building) The major landscaping is done and soon we can finish up the rest of the exterior I hope.

We have been moving at an incredible pace. I've done a lot of push jobs before, but this one takes the cake. Interior shots don't tell the story anymore, but here is a new outside picture.